مرکز اطلاعات علمی Scientific Information Database (SID) - Trusted Source for Research and Academic Resources

Persian Verion

Scientific Information Database (SID) - Trusted Source for Research and Academic Resources

video

Scientific Information Database (SID) - Trusted Source for Research and Academic Resources

sound

Scientific Information Database (SID) - Trusted Source for Research and Academic Resources

Persian Version

Scientific Information Database (SID) - Trusted Source for Research and Academic Resources

View:

841
Scientific Information Database (SID) - Trusted Source for Research and Academic Resources

Download:

176
Scientific Information Database (SID) - Trusted Source for Research and Academic Resources

Cites:

Information Journal Paper

Title

THE PREEMPTIVE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM SUBJECT TO DUE DATES AND PREEMPTION PENALTIES: AN INTEGER PROGRAMMING APPROACH

Pages

  35-39

Abstract

 Extensive research has been devoted to RESOURCE CONSTRAINED PROJECT SCHEDULING problem. However, little attention has been paid to problems where a certain time penalty must be incurred if activity preemption is allowed. In this paper, we consider the PROJECT SCHEDULING problem of minimizing the total cost subject to resource constraints, earliness-tardiness penalties and preemption penalties, where each time an activity is started after being preempted, a constant setup penalty is incurred. We propose a solution method based on a pure integer formulation for the problem. Finally, some test problems are solved with LINGO version 8 and computational results are reported.

Cites

  • No record.
  • References

  • No record.
  • Cite

    APA: Copy

    AFSHAR NADJAFI, B., & SHADROKH, S.. (2008). THE PREEMPTIVE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM SUBJECT TO DUE DATES AND PREEMPTION PENALTIES: AN INTEGER PROGRAMMING APPROACH. JOURNAL OF OPTIMIZATION IN INDUSTRIAL ENGINEERING (JOURNAL OF INDUSTRIAL ENGINEERING), 1(PRE. NO. 1), 35-39. SID. https://sid.ir/paper/205922/en

    Vancouver: Copy

    AFSHAR NADJAFI B., SHADROKH S.. THE PREEMPTIVE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM SUBJECT TO DUE DATES AND PREEMPTION PENALTIES: AN INTEGER PROGRAMMING APPROACH. JOURNAL OF OPTIMIZATION IN INDUSTRIAL ENGINEERING (JOURNAL OF INDUSTRIAL ENGINEERING)[Internet]. 2008;1(PRE. NO. 1):35-39. Available from: https://sid.ir/paper/205922/en

    IEEE: Copy

    B. AFSHAR NADJAFI, and S. SHADROKH, “THE PREEMPTIVE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM SUBJECT TO DUE DATES AND PREEMPTION PENALTIES: AN INTEGER PROGRAMMING APPROACH,” JOURNAL OF OPTIMIZATION IN INDUSTRIAL ENGINEERING (JOURNAL OF INDUSTRIAL ENGINEERING), vol. 1, no. PRE. NO. 1, pp. 35–39, 2008, [Online]. Available: https://sid.ir/paper/205922/en

    Related Journal Papers

    Related Seminar Papers

  • No record.
  • Related Plans

  • No record.
  • Recommended Workshops






    Move to top